How to display Primavera P6 dates in mmm-yy format
There are times you might want to display approximate dates in a Primavera P6 schedule layout by excluding the day part of date so that you only show the month and year parts of a date. For example, you might want to show Dec-21 instead of 05-Dec-21.
By default, Primavera P6 format options are limited and does not offer the functionality to display only month and year (to the best of my knowledge) but there is a workaround by using User Defined Fields (UDF) with a Global Change function.
The YouTube below outlines the workaround steps to follow to display dates in mmm-yy format in a Primavera schedule layout.
Do you have gaps on activity bars after the data date for activities that are in progress in Primavera P6? Get rid of the gaps with this quick tip.